wp00dbe43b.png
wp667f4155.png
wpe9edff41.png
wp6ff59df0.png
Brickkickers new home inspections
Share |
wp87468881.png
wpfde80cfa.png
wp0f2873e2.png
wp50c64294.png
wp407be86c.png
wp887431be.png
wp887431be.png
wp887431be.png
wp37c972aa.png
wp37c972aa.png
wp887431be.png
Page copy protected against web site content infringement by Copyscape
     © 2006 - 2011 brand-newhomes.co.uk - All rights reserved
wped21c001.png
wp9abea487.png

This is the date when each of the builders’ regions have to report to their group head office, how many completions were achieved, that is homes they have built and sold, within their financial year. This is then released as either final (annual) or interim (half-year) results in their company accounts for their shareholders.

 

It is crucial for each region to achieve their target number of completions and everything is done to ensure they reach the required figure. Sometimes the house builder’s regional directors can lose substantial bonuses amounting to 30% - 50% of salary (and sometimes their jobs) if the target figures are not met. Very often your home is rushed to be finished in time for you to complete the purchase before the 'year-end' cut off date. This can result in a low standard of finish and reduced or forced drying out.

 

In the past it has been known that  large cheques were given to purchasers to persuade them to complete the purchase on their new home - even though it had not been finished, or remain in their old 'part-exchanged' home whilst their new home was finished. This cannot now occur, as the Council for Mortgage Lenders’ (CML) initiative requires builders to obtain a completion certificate. This is issued by an independent Building Inspector, normally the NHBC, following a satisfactory final inspection of the property and is required before the lender will release mortgage funds. However a cash purchaser may not necessarily have this protection and should ask for the 'CML' before legally completing the purchase of the property.

 

Listed below are some of the national builders  'End of year' dates.

Builders’ End of year figures

wp7b31d765.png
wpb9f8eb2a.png
wp9b35775f.png
wpbe7e3032.png

Developer / Builder

 

 

Persimmon Homes (Charles Church)

Taylor Wimpey (Inc. George Wimpey, Laing Homes & Bryant Homes)

Barratt Developments

(Inc. David Wilson Homes)

Berkeley Group

Bellway Homes

McCarthy & Stone

Bovis Homes

Redrow Group

Crest Nicholson

Bloor Holdings

Keepmoat Homes

Fairview Homes

Miller Homes

Kier Group (Bellwinch, Twigden)

Linden Homes (Galliford Try)

Croudace Homes

Countryside Properties

Gladedale Homes

Gleeson Homes

Cala Group

 

Interims

 

 

30 June

30 June

 

31 December

 

31 October

31 January

28 February

30 June

31 December

30 April

31 December

30 September

30 June

30 June

31 December

31 December

31 December

31 March

30 June

31 December

31 December

Finals

 

 

31 December

31 December

 

30 June

 

30 April

31 July

30 August

31 December

30 June

31 October

30 June

31 March

31 December

31 December

30 June

30 June

30 June

30 September

31 December

30 June

30 June  

 

wp52527b12.png
wp25764374.png