






Around 160,000 new homes are built each year in normal market conditions and most
of these will have had defects at the time of occupation. The number of defects or
'snags' found in new homes has been steadily increasing each year. In 2005, the average
number of snagging defects per home was 62. Now you can expect to find at least 40
problems in a one-
Insufficient build time Planning delays
Non standard designs built Fewer Inspections
Self Employed tradesmen Lack of skilled tradesmen
Why are standards getting worse?
There are many potential reasons that could explain why new homes built this year will have more defects and be of a generally lower quality than those built five or even ten years ago. Chris Wood has completed a study into why defects occur in new homes less than ten years old. Whilst the study confirmed there are many reasons for defects in new homes, he found that the root cause was connected with professionals within the industry placing profit above quality.
As part of the research questionnaires were sent to various disciplines working in
the house building industry: 35% Warranty inspectors, 16% Quantity Surveyors, 17%
Clerk of works/quality inspector -
Owing to the increase in the number of homes built each year and the increased workload due to building control inspections, the warranty providers now normally only inspect a new home at six 'key stages' of construction. They no longer carry out random spot checks and are contacted by the site manager (unless he forgets) when an inspection is required. This can mean that the warranty inspector only checks the stage he has been asked to look at and he may not visit the site for a number of weeks between stages. The decrease in the number of independent inspections can only contribute to lower standards and increased incidents of defects.
The construction industry has known for some time that there would be a time in the
future, when there would be a shortage of skilled tradesmen to build the number of
new homes required. The Construction Industry Training Board (CITB) was formed as
long ago as 1964 to promote and improve the standard of training within the industry.
However the issue of the lack of skilled tradesmen has still yet to be addressed.
A point was reached a few years ago when there were insufficient plumbers and plasterers
to meet the workload. As a result of the shortage many sub contractors are left with
no option but to employ operatives with limited knowledge and skill, or pay over-
Fewer apprentices
Some of the larger house builders have a policy of employing apprentices, as their way of 'giving something back' to the construction industry. The reality is that the apprentices that are employed, are placed with sub contractors and paid below the minimum wage (because they are receiving training).
Insufficient time to build – unrealistic build programmes
Over recent years, the time taken to build the average house has decreased. This
has been achieved in part due to advances in technology, materials, construction
methods and off site manufacturing. However, even with all the current efficiencies
being adopted, the time given to build your new home continues to decrease. Some
house builders allow 12 weeks or less to build the average home, placing a burden
on the under-
The skill shortage has resulted in price rates for each operation increasing dramatically over recent years. It is not uncommon for a tradesman to start on site at 7.30am and have earned 'enough' (circa £1000 per week) by 2pm and leave the site for the day. This results in even less work being completed but the build programme remains unchanged.
There is growing incidence of the planning process delaying the start of new developments. When planning permission is eventually given, there can be a rush to start work on site in an effort to make up the time lost. This can have even more relevance if the site has a contribution to make to the company’s end of year figures. However, planning delay often causes a knock on effect with both architectural and structural information being required within an unrealistic time frame, often resulting in mistakes on the working drawings, many drawing revisions and problems on site. Overcoming a design problem on site, especially once a section of work has been completed usually involves remedial work or a compromise. This, together with a reduction in the available time to complete the required number of homes to meet the target figures, adversely effects quality.
Non standardised designs being built
Most of the larger house builders have a set of standard house designs that are built
throughout the country. Only the type of brick, roof tile, and to a lesser extent
windows, differing to suit the locality. However, due to planning delays, many of
the larger builders, having inherited an approved design with the land acquisition,
are choosing to build non-

Problems with new homes:
Why new homes have so many defects
What to do when you discover a problem
How to complain to the house builder
Who are the best house builders
What you need to know about timber frame new homes
Fire and timber frame new homes
Considerations when buying a flat
Buying a new home in a recession
What you should know about timber frame

Poor workmanship
Lack of Inspections
Use of Sub Contractors
Poor/impractical designs
Lack of skilled labour
Poor communication on site
Other
Reasons why defects occur in new homes

39%
17%
5%
8%
8%
8%
15%
